Six weeks at sea sounds like a problem. It’s a pipe you fill once.
On June 20, 1977, oil began flowing into the Trans-Alaska Pipeline at Prudhoe Bay. It took 38 days to travel 800 miles to the port of Valdez.
Nobody worried that the oil took 38 days. Once the first barrel reached the end, oil arrived every day after that. The wait happened once.
A container from Nhava Sheva, near Mumbai, to New York takes about the same: 38 days at sea, on average, this summer.
How long the trip takes
By air
Door to door, for samples, first parts and urgent top-ups
about 1 week
By sea to Rotterdam
Port to port from Nhava Sheva, near Mumbai
3–5 weeks
By sea to New York
Port to port from Nhava Sheva; 38 days on average in mid-2026
5–6 weeks
Air is for samples, first parts and emergencies. Everything else goes by sea, so the real question is what those weeks do to you.
Order every month, and a shipment lands every month
Order monthly, receive monthly
Illustration: about three months from the first order to the first delivery, covering production, the trip to the port, about 38 days at sea and the last leg. Your quote confirms the timing for your part. After that, a shipment lands every month.
The first shipment makes the whole trip. After that, monthly orders become monthly deliveries, and the weeks at sea become a pipe you’ve already filled. What still makes the full trip is a change: a new part, a sudden spike, a forecast that was wrong. The four steps below take care of those.
The real cost is the stock at sea: about 1–3%
Yearly cost of six weeks at sea
As a share of what you spend on the parts. Six weeks in transit is 6/52 of a year’s purchases. Interest at 7% a year; 25% is the top of the 15–25% range planners commonly use for all holding costs. Sea time: ShipsGo, June 2026. Pipeline: Petroleum News.
Six weeks of parts are always afloat, and that stock ties up money. Count only the interest, and it’s under 1% of what you spend in a year. Add everything planners usually count, like storage, insurance and parts going out of date, and it’s about 3%.
How to plan the first months
Order on a rhythm
The same quantity on the same day each month is easier to plan than one big order, for you and for the factory.
Share a forecast
Three months’ view lets the supplier plan production before your order arrives.
Keep a small buffer at first
A few extra weeks of stock until the rhythm is proven. Each extra week costs about half a percent of a year’s spend.
Fly the first parts
Samples and the first production parts can come by air in about a week, while the first sea shipment is on its way.
Nobody remembers the 38 days it took the first oil to reach Valdez. They remember that it never stopped coming.
Weeks at sea are one kind of distance. The hours between your question and its answer are another.

Want to see the rhythm for your part?
Send a drawing, your yearly quantity and your delivery address. We’ll quote with the timing for each shipment.